Installation of I&C systems and elements of the HDCS system along with the delivery of material Czechnica CHP Plant, Siechnica
Project description
Installation and delivery of materials and instrumentation equipment necessary to connect instrumentation and instrumentation devices for the installation of the Gas and Steam Unit (BGP), including:
- installation of complete measurement systems, including installation of control and measurement equipment, manometric valves and valve manifolds, installation of impulse tubes, installation of vessels, level, installation of measuring stands,
- cabling installation – signal/control and I&C communication cables,
- installation of cable structures for instrumentation and control cables, including installation of protective pipes,
- installation of instrumentation and control cabinets, junction boxes and protective cabinets,
- installation of computer equipment and other elements of the HDCS system at the signal box.
- other, required to connect I&C equipment and devices to technological installations and cabling from control and measurement equipment, cabinets and devices, through field signal boxes to the terminals of the HDCS system.
Project details
- Category: Electrical and I & C Installation, Gas power generation
- Project location: Czechnica CHP Plant, Siechnica
- Project date: 2022-2024
- Project contractor: Polimex Mostostal S.A.