Adaptation of emission monitoring systems on units 1-6 BAT requirements regarding equipment for measuring Hg, NH3, HCl and HF in waste gases, Opole Power Plant
Project description
The scope of the order included:
- Design (execution, as-built, quality documentation) in the scope of all industries necessary to complete the subject of the order, obtain the approval of the project by the Ordering Party and comprehensive deliveries and services for the facility part of the monitoring system, including: facility equipment, accessories, cabling, power supply, in the scope necessary for the construction of double-walled chimney flues in blocks 1-4 and flue gas ducts behind the FGD in blocks 5-6.
- Carrying out all necessary disassembly, assembly, commissioning and inspection works related to the proper operation of the installed elements
- Performing post-installation checks, including commissioning of the modernized installations and devices, along with checking the readings of measurement values and binary signals, including the operator panel and the exhaust emission accounting system.
Project details
- Category: Conventional power generation, Electrical and I & C Installation
- Project location: Opole Power Plant
- Project date: 2020-2021
- Project contractor: SICK SP. Z O.O.