gas
July 23, 2024
Comprehensive assembly and delivery of equipment, cables and I&C equipment, Dolna Odra Power Plant, Nowe Czarnowo
Installation and delivery of materials and instrumentation equipment for the installation of the Gas and [...]
Read moreJune 13, 2024
Gas boiler room, Kielce CHP Plant
Turnkey construction of a gas boiler room for five gas water boilers each with a thermal capacity of 32MW [...]
Read moreJune 13, 2024
Construction of a gas-fueled cogeneration source based on a set of gas engines with a power of up to 50 MWe, Gdynia CHP Plant
Construction of a gas-fueled cogeneration source based on a set of gas engines with a power of up to 50 MWe [...]
Read moreJune 13, 2024
Revitalization of the boiler plant of Unit 7-230 MW, Kakanj, Bosnia and Herzegovina
Revitalization of the boiler plant of Unit 7-230 MW for the needs of the Kakanj TE branch. Engineering of [...]
Read moreJune 12, 2024
Constraction of CCPP, CHP Czechnica Plant, Siechnica
Performing chemical cleaning and steam blowing of two recovery boilers and steam pipes. Scope of work: [...]
Read moreJune 12, 2024
Commissioning a steam boiler using gas fuel with a capacity of 100 t/h along with auxiliary installations, Grupa Azoty Zakłady Azotowe Kędzierzyn S.A
As part of the project, a peak and reserve boiler room with a capacity of 100 tons of steam/h along with [...]
Read moreJune 12, 2024
Commissioning of CCPP, Wolfsburg, Germany
Participation in the commissioning works of two gas and steam units with a total electrical power of 288 MW [...]
Read moreJune 12, 2024
Assistance with the operation of the Gas-Steam Unit in Stalowa Wola CHP Plant
Technical advice and assistance in the operation of the 450MW Gas and Steam Unit.
Read moreJune 12, 2024
Constraction of CCPP, Żerań CHP Plant, Warsaw
Providing services associated with CCPP commissioning at Żerań CHP Plant in Warsaw (496 MW)
Read moreJune 12, 2024
Commissioning of CHPP, Stalowa Wola CHP Plant
Commissioning of CHPP in Stalowa Wola CHP Plant.
Read moreJune 12, 2024
Installation of SCRs in Dolna Odra Power Plant, Nowe Czarnowo
Turnkey construction of a catalytic denitrification installation with accompanying infrastructure for units [...]
Read moreJune 1, 2024
Installation of I&C systems and UDCS system elements along with the implementation of materials in CHP Czechnica Plant, Siechnica
Installation and delivery of materials and instrumentation equipment necessary to connect instrumentation [...]
Read moreMay 24, 2024
Providing specialized and comprehensive operational services in CHP Czechnica Plant, Siechnica
The aim of the project is a new, low-emission, environmentally friendly investment. The power source is [...]
Read more