We are pleased to announce that on 20th June a ceremonial summary of t” took place.

The contract implemented by SBB ENERGY consisted of 6 stages, during which 6 boilers in the South Heat Plant and 4 boilers in the North Heat Plant were modernized and expanded with a flue gas cleaning installation.

Thanks to this investment, both heat plants can operate in accordance with new environmental regulations, guaranteeing Radom residents an environmentally friendly heating system.

This was a big investment challenge, which was met mainly thanks to the commitment and excellent work of the entire project implementation team.

Congratulations!