he completion ceremony of the project “Construction of the flue gas cleaning system” at the Łąkowa II Heat and Power Plant in Grudziądz took place on 29.11.2022.

The investment lasting over 4 years was designed to achieve emission standards beeing in line with the new EU directive.

Some numbers and facts:

Investment value –  PLN 64.3 million net.

As a part of the investment, the following were made:

  • 3 semi-dry flue gas desulphurisation / dedusting installations for OR-32 steam boilers (K1, K2, K3);
  • 2 flue gas dedusting installations for WR-25 water boilers (K4, K5);
  • 3 SNCR flue gas denitrification installations for OR-32 boilers (K1, K2, K3);
  • Flue gas denitrification installation using primary methods for WR-25 (K4, K5) boilers;
  • Construction of an ammonia water unloading and storage station;
  • Construction of a sorbent and PPR unloading and storage station
  • Replacement of the façade of the boiler house, repair of existing roads and squares in the investment area;

The individual stages of implementation were commissioned according to the schedule in the years:

  • IOS K1, K2 – 30.11.2020
  • SNCR K1 – 15.03.2021
  • IOS K3 – 30.11.2021
  • SNCR K2, K3 – 30.06.2022
  • Completion of the investment – 30.10.2022

Huge congratulations to the entire team involved in the successful implementation of this project, because people are behind the success of this project!