NEWS

Our specialists will implement a system of flue gas cleaning installation for OR-32 and WR-25 boilers

Positive information continues. Our specialists will implement a system of flue gas cleaning installation for OR-32 and WR-25 boilers located in Łąkowa II CHP belonging to OPEC-INEKO Sp. z o.o.

The investment is designed to achieve emission standards beeing in line with the new EU directive.

We wish good luck and successful implementation of the project to the entire team coordinating the contract.

 


2018-09-27

Contract for delivery and assembly of a catalytic denitrification installation in blocks 5, 6, 7, 8 of OP-650 type boilers in Dolna Odra Power Plant.

It is our great pleasure to inform that today i.e. September, 25th SBB ENERGY SA signed a contract for delivery and assembly of a catalytic denitrification installation in blocks 5, 6, 7, 8 of OP-650 type boilers in Dolna Odra Power Plant.

 We are signing this contract for the Consortium lead by SBB ENERGY SA whose partners are Polimex Energetyka Sp. z o.o. and Polimex-Mostostal S.A.

We wish all people involved in this project its effective accomplishment.


2018-09-25

SBB ENERGY S.A. signed a contract for the modernization of three BP-1150 boilers in Opole Power Plant

We are pleased to announce that on 12th June 2018 a contract between PGE GiEK.SA El. Opole and SBB Energy S.A. for the modernization of three BP-1150 boilers was signed. The aim of modernization is to reduce the emission of nitrogen oxides NOx below 150 mg / Nm3.


2018-06-13

LATEST PROJECTS

  • Principal:
    EDF Polska S.A. Elektrociepłownia Gdynia
    Customer:
    EDF Polska S.A. CHP Gdynia
    Scope of work:

    Execution of installation works in the construction of primary and SNCR methods plant on two boilers BC-50 in CHP Plant in Gdynia as General Constructor.

  • Principal:
    Veolia Energia Poznań - Zespół Elektrociepłowni S.A.
    Customer:
    CHP Poznań
    Scope of work:

    Execution of installation works in the construction of DeNOx by SNCR method on boilers 1K2, 2K, 3K in CHP Plant Karolin in Poznań.

  • Principal:
    ELEMONT SP. Z O.O
    Customer:
    PGE GiEK S.A. Oddział Elektrownia Opole
    Scope of work:

    Installation and lightening in buildings 5UHA and 6UHA in the construction of power units in Opole Power Plant..

  • Principal:
    KRALOPOLSKA RIA - Elektrownia Chvaletice w Czechach
    Customer:
    CHP Chvaletice, Czech Republic
    Scope of work:

    DeNOx installation for two boilres K3 and K4.

  • Principal:
    Veolia Energia Poznań - Zespół Elektrociepłowni
    Customer:
    CHP Poznań
    Scope of work:

    DeNOx system installation for all three units.

  • Principal:
    EDF Polska S.A. Elektrociepłownia Gdynia
    Customer:
    CHP Gdynia
    Scope of work:

    Adaptation of boilres to meet the requirements for NOx emmisions using primary and secondary SNCR methods.

  • Principal:
    Elektrociepłowania Będzin Sp. z o.o.
    Customer:
    CHP Będzin
    Scope of work:

    Execution of installation works in the construction of DeSOx and DeNOx in CHP Plant in Będzin for boilres no. 7, no.6, no.5 as General Contractor.

  • Principal:
    Andritz Energy&Environment GmbH
    Customer:
    Mjölby / Sweden
    Scope of work:

    Commissioning works on biomas unit in Mjölby, Sweden

  • Principal:
    E.ON ENERGY
    Customer:
    Marl / Germany
    Scope of work:

    Start ups in Chemical Industrial Plant

  • Principal:
    ALSTOM s.r.o.
    Customer:
    Ledvice/Czech Republic
    Scope of work:

    Commissioning works on unit 660 MW in Ledvice,  Czech Republic

REFERENCES: